titleCompleted
  • July 2023

    •  Inventory and evaluation of hardware and networking components

  • Mid-August 2023

    • Continue to evaluate all hardware and networking components

    • Notify private partition and node owners in advance of the October move

  • September 2023

    • Plan logical hardware move schedule

    • Prep Iron Mountain (IM), the new data center space.

    • Review plan with private partition and node owners that will be integrated into the Sol supercomputer

  • October 2023

    • Establish the “Phoenix” supercomputer at IM with ASU Research Computing owned equipment

    • Begin moving Sol-capable private nodes into Sol

    • Notify private partition and node owners in advance of the November move

  • November 2023 - The project hit an unexpected delay

  • February 2024 - Project Resumes

    • (19th) Notify Private Partion Owners of Project Restart and Timeline

    • (22nd) The Phoenix supercomputer is available for testing by private partition owners.

    • (26th) Notify Private Partition Users and node owners in advance of any moves into Phoenix

  • March 2024

    • (~11th) Reminder to Agave users of Agave access and scratch data removal for May 13th, 2024

    • (11th) Remind private partition and node owners in advance of any moves into Phoenix

    • (25th) Move the 1st Wave of Agave private nodes into Phoenix

    • (26th) Notify Private Partition Users and node owners in advance of any moves into Phoenix

    • (26th) Remind Private Partition Users and node owners in advance of any moves into Phoenix

  • April 2024

    • (1st) Reminder to Agave users of Agave access and scratch data removal for May 13th, 2024

    • (1st) Remind Private Partition Users and node owners in advance of any moves into Phoenix

    • (22th) Reminder to Agave users of Agave access and scratch data removal for May 13th, 2024

  • May 2024

    • (1st, and each day for those with data remaining) Reminder to Agave users of Agave access and scratch data removal for May 13th, 2024

    • (13th) Physical move, upgrade, and rebuild of remaining equipment into Phoenix

  • June - August November 2024

    • Power supply units for 324 nodes require replacement. Replacement PSU sourcing has experienced significant delays.

  • December 2024

    • Replacement PSUs arrive

  • January 2025

    • Expected public access to Phoenix. The exact date to be determined

...